| 1) Project Procurement |
| |
• Identifying Target Markets
• Developing niche markets
• Identifying markets where competitive advantage exists |
| |
| Identifying Key Owners |
| |
• Identifying and obtaining work from
good owners
• Identifying owners who are difficult
• Determining where profit returns will justify risk |
| |
| Initial plan review and prioritization of
bid opportunities |
| |
• How does a contractor determine
which opportunities to pursue aggressively, which to load profit on and
when not to bid at all
• Initial review of plans to determine if advantage exists
• Prioritizing/ranking of bid opportunities
• Which do we want to bid?
• Which do we have to bid?
• Coordination of bid between project management and estimating,
determination of resources (people available and how that influence
bid) |
| |
| Bid preparation/estimating |
| |
• Sub advertising
• Designing scope for each sub
• Fulfilling MBE/DBE/WBE requirements
• Sub prequalification/bonding
• Determination of when not to use lowest bidder
• Ethics-bid shopping |
| |
| Post bid review |
| |
• Formalizing commitment form subs
• Identifying overlapping items in bids/missing items
• Analyzing how competition bid-higher, lower and Why? |
| |
| Consider having the intern participate in
or sit in on: |
| |
• Senior management discussions about
what makes the contractor different where the following are
addressed: |
| |
|
1. How does the company differentiate itself from the
competition?
2. What does the company have as strategic advantages as a result of
resources, equipment, people, etc.?
3. How does the company take advantage of its strength?
4. What is its niche? |
| |
• Management strategy meetings
discussing current project opportunities where the following are
addressed: |
| |
|
1. What factors go into the contractor’s decision
about what projects should be bid.
2. Solicitation of subs and MBE/DBE/WBE bids. |
| |
• Walk through of formal
prequalification process for subs, if there is one.
• Observation of bid day to witness how hectic putting a bid
together can be.
• Post-bid evaluation by estimating to either determine how and
why the competition won, or to verify the bid was a good one, and that
nothing was missed prior to accepting the contract. |
| |
| The whole project procurement process
from developing strategy to post-bid evaluation could be covered in a
couple of days, or it could be spread out over the course of the week so
as to fit the bidding/estimating schedules. |
| |
| 2) On Site Project Management |
| Spend a couple of days in the field for
in-depth perspective, whether it be on one project, or spread over
multiple projects. Some of the key aspects that need to be covered
are: |
| |
• Chain of command-when to escalate
problems
• Scheduling-working with subs and suppliers to achieve timely
project completion
• Subcontractor progress meetings
• Developing cost to complete figures
• Monitoring budget vs. actual
• Change order preparation
• Documenting changes. Changed conditions, alternatives and cost
for claims
• Project close-out
• Safety program |
| |
| Past interns have found it helpful to
visit a project that is just starting (to observe how the project
manager gets all parties to buy into the plan for building the job), to
visit a project that is further along, and to visit one in the closeout
stage. |
| |
| 3) Monitoring Progress and Management
Controls |
| Management involvement and continued
monitoring of projects and people are essential to the long term success
of any organization. Consider addressing: |
| |
• How does senior management stay on
top of operations w/o being involved in day-to-day construction
operation? Is it necessary for senior management to get their hands
dirty?
• How are estimating and project management people evaluated? How
are they developed?
• What types of Incentive programs have worked best to motivate
people?
• How often does management visit projects and independently
communicate with owner reps to determine owner satisfaction? When does
management gets directly involved in a specific project?
• What is their method of communication between departments? How
do they avoid finger pointing or blame (it was a bad bid, project
manager was no good, etc.) How does management develop a sense of
teamwork and honest evaluation of performance?
• What financial tools does management use to monitor
performance?
• Setting goals for all areas of the organization: How to motivate
people to reach goals.
• How teams are built within the company?
• What is the culture of the organization?
• Developing business plans |
| |
| The process of learning about management
control and evaluation of people and progress can be handled within the
course of a single day. |
| |